Upgrid gas pressure regulating and metering plant Steinitz

New construction of the metering and control track 10 as redundancy to the MRS 9

Steinitz (Saxony Anhalt) Germany

  • Construction of a measuring and control line DN 600, DP 100
  • Integration into existing underground lines
  • Inlet and outlet DN 800 with complete underground construction
  • Measurement building in sheet metal profile construction

Civil engineering with necessary closed dewatering and 630 m³ support pile wall shoring up to a foundation depth of 5.0 metres

May to November 2019

ONTRAS Gastransport GmbH