Natural gas pipeline ZEELINK Lot 4+

Pipe-laying and civil engineering works for the new construction of the Zeelink natural gas pipeline, construction lot 4+.

Section St. Hubert station to the Dämmerwald valve station

  • 61.3 km DN 1000, DP 100
  • 3.6 km DN 1000 in construction lot 3
  • 9.5 km DN 1000 in construction lot 5
  • New construction of 4 valve stations and 1 pigging station
  • Rhine culvert over 525 m length (1050 to)
  • Crossing the Wesel-Datteln canal and the Lippe River (micro-tunnel DN 1600, 290 m long)
  • 36 crossings using the drill-press method of various rural, district and federal roads as well as motorways and railway lines with lengths between 22 and 97 m
  • 3 crossings using the direct pipe method (product steel pipe DN 1000, “Tote Rahm” approx. 85 m,    
  • K23 road approx. 42 m, Hörstgener Kendel approx. 41 m)
  • Execution in joint venture with HABAU Hoch- und Tiefbau GmbH

April 2019 until March 2021